mixed carnac and vikhroli rail overbridges near completion set to open in june

Carnac And Vikhroli Rail Overbridges Near Completion, Set To Open In June

4hrs 8mins   👁 5

The deck slab on the western side is ready, while a 40-metre stretch on the eastern side is currently undergoing curing. To expedite the process, BMC has used early strength concrete, which will enable the road surface to be traffic-ready by June 5